Floating system immersion large dry dock

Floating system immersion large dry dock

In collaboration with "VolkerRail Nederland BV", High Point / Buitink Technology has produced and installed a floating (inflatable) system designed to support the launching and immersion of a large dry dock.

This dry dock is used for the repair activities of the "Grave" dam, which was badly damaged following a collision in December 2016.

In addition to the installation, we sent a team of specialists on site to control the floating system.

The floats are 3.5 m long and 1.8 m in diameter. They can lift about 9000 kg.

Données du projet:

Client:
Rijkswaterstaat
Consultant: Ingenieursbureau Boorsma BV
Client Buitink: VolkerRail Nederland BV
Système flottant: Buitink Technology

More information